Project Description

Küttner GmbH & Co. KG

Erection of a coal injection system for 3 furnaces in Linz, Austria

Küttner GmbH & Co. KG commissioned VIB with the project management for a new construction of a coal-grinding and drying plant for three furnaces (Furnace A, 5 and 6) in Linz for the voestalpine Stahl GmbH.

The raw coal is stored in the port area and gets then prepared in a plant.

Subsequently, the raw coal is milled and dried in the coal-grinding and drying plant.

The produced fine coal gets transported to the coal infection system by pneumatic transport and is temporarily stored.

Then the fine coal gets distributed to the individual furnaces and is blowed into the blow mouldings.

The VIB services rendered:

  • Order control and monitoring
  • Project coordination
  • Schedule controlling
  • Monitoring overall time scheduling
  • Pursuit commissioning of the plant
  • Claimmanagement
  • Reporting, project documentation

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.