Project Description

Net4Gas, s.r.o.

The new construction of the GAZELLE gas pipeline in the Czech Republic

The connection between the German gas pipelines OPAL and MEGAL passing through the Czech Republic has been complete in January 2013. The builder and the gas network operator is NET4Gas, a subsidiary of RWE AG.

The pipeline with a tube diameter of
1.4 metres is designed to carry a gas pressure of around 73 bar and passes through the Czech Republic for about 160 km.

The Brandov Station (see illustration) is the northern junction transfer point and was commissioned on schedule on 1st October 2011.

VIB has supported Net4Gas since November 2010.

The VIB’s tasks:

  • Project organisation and execution
  • Time schedule and schedule control
  • Reporting and project documentation
  • Supplementary works and claims management
  • Project monitoring and controlling

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.