Project Description

Rasselstein GmbH

Capital investment projects extension to Works 2 in Andernach

Rasselstein GmbH extended its works between 2003 and 2005 in Andernach for a total capital investment of some EUR 160 million. Investments included the construction of a new continuous annealing furnace, the reconstruction of a refining plant from Dortmund as well as a finished goods warehouse with consignment hall. The purpose of the investment was to increase the capacity in the production of white metals.

The initial infrastructure measures on the construction site were commenced in the spring of 2003. The main contracts for the plant components were awarded in November 2003.

Commissioning was commenced in the spring of 2005, so that full production status could be achieved by the end of 2005.

In the framework of the project management, VIB was responsible for:

  • Setup and process organisation
  • Controlling and monitoring of the contract works
  • Schedule planning, time schedule, deadline monitoring
  • Cost planning, controlling and monitoring
  • Reporting and documentation
  • Procure management

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.