ThyssenKrupp Nirosta GmbH

DR1600 Skin-pass mill

This specified ‘skin-pass mill’ is intended for the production of high-grade stainless steel coils of austenitic, ferritic and martensitic stainless steels as well as titanic stainless steel at high production rates over long periods of time under conditions of continuous duty, within a steel typical environment.

For these reasons, the skin-pass mill has to meet the highest applicable technical and production-technical standards and represent the latest technical, manufacturing and automatic states-of-the-art.

The building construction and civil engineering works commenced in March 2011 and were already largely completed by August 2011.

The installation of the plant components commenced in August 2011 and was concluded in December 2011.

Immediately thereafter, commissioning of the cold and annealing processes were commenced and completed in May 2012.

In the framework of the project management, VIB was responsible for:

  • Order controlling and monitoring
  • Deadline monitoring and time schedule
  • Cost monitoring and controlling
  • Project documentation, reporting
  • Support services during commissioning

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.