Project Description

ThyssenKrupp Nirosta GmbH

New construction of the KL3 cold rolled strip production line in Krefeld

Within the scope of its capacities expansions, ThyssenKrupp Nirosta GmbH erected a new cold rolled strip production line for stainless steel at its Krefeld Works, which was officially commissioned in June 2003.

The plant is accommodated in a 240 metre long and 27 metre wide hall and serves the processes of annealing, pickling, temper-rolling and trimming of high-grade quality cold-rolled stainless steels in gauges between 0.2 and 2.0 millimetres.

The plant has a reference capacity of some 40 metric tonnes per hour, corresponding to 220,000 metric tonnes each year.

The projected plant was able to be commissioned two months earlier than foreseen, and the planned run-up curve was exceeded.

In the framework of the project management, VIB was responsible for:

  • Project organisation and coordination
  • Time scheduling, controlling and monitoring
  • Cost planning, controlling and monitoring

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.