Project Description

ThyssenKrupp Nirosta GmbH

The reconstrution of the KL3 and GBL3 annealing- and pickling production line in Krefeld

As a result of fire damage in the Thyssenkrupp Nirosta Krefeld Works in 2006, the KL3 cold strip rolling mill as well as the GBL3 annealing and pickling production line were seriously damaged.

Both production lines had to be reconstructed under considerable pressure of time.

VIB had already supported the new construction of the KL3 cold strip rolling mill between 2000 and 2003, so that considerable knowledge concerning the plant was already available.

Overall, the challenging targets of the project were more than simply fulfilled.

The originally specified deadlines for commissioning were undercut, the run-up curve more than fulfilled, commissioning and the acceptance of capacity was earlier than anticipated.

The VIB services rendered:

  • Schedule planning, time scheduling, deadline monitoring
  • Order controlling and monitoring
  • Coordination, controlling and testing of the repair and renovation works
  • Finalising documentation

VIB GmbH • Competence since 1977

We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.

Feel free to contact us…