Project Description
After the fire in august 2011 in the steel plant in Schwerte-Ergste, the PS-production should be rebuilt as soon as possible at the location in Unna.
The package to be realized for the Unna site included the construction of a new hall with the required machine technology and the ancillary facilities.
The plant engineering includes:
- 1 Vertical bright annealing line
- 1 Horizontal bright annealing line
- 1 Rolling mill
- 1 Continuous annealing line
- 1 Tension leveler system
The VIB services rendered:
- Schedule controlling including monitoring of the overall time planning
- Preparation, coordination and recording of status talks
- Coordination between all trades
- Project monitoring in the form of status reports or presentations for the management board
Pursuit of construction and assembly processes including plant commissioning
VIB GmbH • Competence since 1977
We support worldwide private as well as public investors in project management and steering. For nearly 40 years we successfully handle projects in fields of Plant construction, Power plants, Coking plants, Smelting plants, Universities, Administration and Office buildings, Research Centers, Schools and Technology Centers.